How to Track Material Deliveries in Daily Logs
Material delivery tracking construction sounds like paperwork—until you’re the one explaining a missing pallet to accounts payable, or fighting a backcharge because the drywall showed up crushed. A tight construction delivery log isn’t “extra admin.” It’s how you prove what hit the site, what condition it was in, and what you should actually pay for.
Table of Contents
- Why Material Documentation Protects You
- What to Track
- Documenting Damaged Materials
- Template and Examples
- Common Mistakes
- FAQ
Why Material Documentation Protects You
A clean delivery documentation construction process protects you in three places: billing, schedule, and claims.
First, it keeps money straight. If you don’t record what showed up (and what didn’t), invoices roll in for full quantities anyway. Then you’re chasing credits weeks later—when the supplier “can’t find the ticket” and your PM is asking why AP can’t close the month.
Second, it keeps the schedule honest. When the roofer says, “Material’s not here,” you need more than a text thread. You need a timestamped record that the membrane was delivered at 9:10 a.m., placed on the west laydown, and signed by your laborer.
Third, it protects claims. Damage claims live and die on details: condition notes, photos, and who accepted the load. If the bundle sat on site for two days before anyone wrote it down, you’re going to wear that cost.
Two real-world situations you’ve probably seen:
- Billing dispute: Supplier invoices 120 sheets of 5/8" GWB. Your crew only received 100 due to a shorted pallet. Without a construction receiving log entry and ticket photo, it becomes your word vs. theirs—and AP often pays to keep the job moving.
- Damage fight: Curtainwall crates arrive with punctures. If the driver leaves and you don’t note “crate damaged on arrival” plus photos, the vendor can claim it happened after delivery.
Practical takeaway: treat every delivery log entry like it might get read by accounts payable or a claims adjuster later—because it will.
What to Track
The goal of material tracking daily report notes is simple: connect what happened in the field to what gets paid in the office. That means your entries need to be specific enough to match a PO, a ticket, and a line item on an invoice.
Below are the minimum fields that make your log actually useful.
Delivery time
Record arrival time and unload complete time. This isn’t nitpicking—time proves access issues, detention, and impacts.
Examples:
- “8:05 a.m. ABC Ready Mix Truck #12 arrived; pour delayed until 9:00 a.m. due to pump setup.”
- “1:20 p.m. steel studs delivered; unloading complete 2:05 p.m.; lift down for maintenance 20 min.”
Practical takeaways:
- If the truck waits because your gate is blocked, note it. That’s how you defend detention charges—or push them back when they’re not on you.
- If a delivery shows up outside the booked window, write it down. It matters when trades blame each other.
Vendor/supplier
Log the supplier name, and if possible the driver/company (especially when using third-party freight).
Examples:
- “Supplier: White Cap. Carrier: XPO Logistics. Driver: ‘Mike’ (badge # if available).”
- “Supplier: Local Lumber Co. (house truck). Signed BOL: J. Ramirez.”
Practical takeaways:
- Many disputes happen because the invoice comes from Supplier A, but the delivery came via Carrier B. Capture both.
- If you rotate suppliers, don’t write “lumber delivered.” Write who delivered it.
Materials and quantities
Write what you can count and verify. Don’t rely on “looks right.” Record unit of measure (pcs, bundles, LF, CY, pallets) and whether the count is verified or per ticket.
Examples:
- “Delivered: 14 pallets CMU 8x8x16 (verified count), 2 pallets grout bags (per ticket).”
- “Delivered: 3 coils #4 rebar (per tag), heat #A17 noted.”
Practical takeaways:
- If you can’t safely break-wrap and count, mark it: “Qty per BOL; not opened.” That protects you when a short shows up later.
- Always record partial deliveries. A lot of jobs bleed money because “some of it arrived” turns into “we paid for all of it.”
PO/ticket numbers
This is the bridge to money. PO numbers, ticket numbers, BOLs, and packing slips are how AP matches invoices.
Examples:
- “PO #24718 / Packing Slip #88931 attached (photo).”
- “Concrete ticket #103771, mix design 4000 psi air-entrained, 9.5 CY.”
Practical takeaways:
- If you capture only one number, capture the PO. It’s the easiest way for AP to match costs correctly.
- Take a clear photo of the ticket next to your entry. When someone asks three weeks later, you won’t be digging through glove boxes.
Condition on arrival
This is where you win or lose damage claims. Record packaging condition, visible damage, and any exceptions.
Examples:
- “2 bundles insulation delivered wet; plastic torn on top corners. Marked exception on BOL.”
- “(No exceptions) Pallets intact, bands tight, no punctures noted.”
Practical takeaways:
- If it’s damaged, write it in plain words. “Damaged” is too vague. Say “crushed corners,” “fork puncture,” “water exposure,” “broken banding.”
- Note site conditions that matter: rain, muddy laydown, no canopy, etc. That context helps later.
Documenting Damaged Materials
When damaged goods show up, your job is to create a record that’s hard to argue with. Fast, factual, and tied to the right paperwork.
Here’s a process that works on real sites where deliveries aren’t “simple,” loads are mixed, and you’re juggling trades.
- Stop the clock and assess before the driver leaves
- If safe, inspect the most vulnerable items first (corners, edges, top of stack).
- If it’s a mixed load (partial delivery + backorder), confirm what’s actually on the truck.
Example scenarios:
- A window delivery has 20 units, but only 18 are on the truck and two crates are damaged. You need to document both the shortage and damage.
- A roofing load arrives during rain. The top layer is wet and the driver wants to “just drop it.” You need a condition note and photos immediately.
- Write exceptions on the delivery paperwork (BOL / packing slip) Be specific. “Received with damage” doesn’t cut it.
Use wording like:
- “Received 10 of 12 boxes. Short 2 boxes.”
- “Crate #3 punctured; contents may be damaged.”
- “Pallet bands broken; boards loose; corners crushed.”
- Take photos that prove the story Photo recommendations (quick but strong):
- Wide photo showing the full pallet/crate on the truck or at drop.
- Medium photo showing the damage area.
- Close-up showing labels/serial numbers and the damaged spot in the same frame if possible.
- Photo of the ticket/BOL with your exception notes.
Two examples of “good enough to win” photo sets:
- Fork puncture through vapor barrier: (1) full pallet, (2) puncture close-up, (3) label with product code, (4) signed BOL noting puncture.
- Short delivery of fixtures: (1) truck with remaining cartons visible, (2) carton count photo, (3) packing slip showing expected qty, (4) photo of your log entry.
- Segregate and label the damaged material Don’t let it get installed “because we’re behind.” Tag it and move it to a quarantine spot.
Practical takeaways:
- Put a piece of tape on the item: “HOLD—damage on arrival—do not install.”
- If it’s partially usable, note what’s usable vs. not. Example: “12 sheets wet on corners; 8 likely usable after drying; 4 compromised.”
- Notify the right people the same day Damage documentation only helps if it reaches the people who can act.
- Email/text to PM + AP contact + procurement (if you have one)
- Include: PO, ticket, photos, and your recommendation (“reject,” “accept with credit,” “replace ASAP”)
Connection to accounts payable (the money part):
- Tell AP to hold payment or expect a credit tied to that PO/ticket.
- If AP pays the full invoice before the credit is issued, you’ll spend hours clawing it back—or you’ll eat it.
Template and Examples
You don’t need a fancy system to start. You need a consistent construction receiving log format that captures the fields above and fits into your daily report.
Here’s a simple template you can paste into a daily log or use as a checklist.
Material Delivery Log Entry Template
- Date:
- Project / Area:
- Delivery time (arrive / unload complete):
- Supplier:
- Carrier / Driver (if available):
- Material description:
- Quantity + unit (verified or per ticket):
- PO #:
- Ticket / BOL / Packing Slip #:
- Drop location (laydown / floor / gridline):
- Condition on arrival (notes):
- Exceptions noted on paperwork? (Y/N):
- Photos taken? (Y/N) + where stored (album/app):
- Received by (name):
- Action needed (none / credit request / replacement / backorder follow-up):
Example 1: Clean delivery (no issues)
- Date: 1/29/26
- Area: Level 2 east corridor
- Time: Arrive 9:12 a.m. / Unload complete 9:40 a.m.
- Supplier: Ferguson
- Carrier/Driver: Ferguson truck / Driver “S.”
- Materials: Copper pipe Type L 1" (bundles)
- Qty: 18 bundles (verified)
- PO #: 61044
- Packing Slip #: 332191
- Drop location: L2 east laydown by hoist
- Condition: Pallets intact, bands tight, no visible damage
- Exceptions: N
- Photos: Y (ticket + pallet overview)
- Received by: T. Nguyen
- Action: None
Why this matters financially: AP can match the invoice to PO #61044 without calling you, and there’s proof the full quantity hit the job.
Example 2: Partial delivery + shortage
- Date: 1/29/26
- Area: Roof
- Time: Arrive 6:55 a.m. / Unload complete 7:35 a.m.
- Supplier: ABC Roofing Supply
- Carrier/Driver: 3rd party / Trailer #KX291
- Materials: TPO membrane 60 mil (rolls), ISO board 2" (bundles)
- Qty: TPO 24 rolls (per ticket); ISO 18 of 24 bundles (verified). Short 6 bundles.
- PO #: 77502
- BOL #: 90811
- Drop location: Roof west side (staged and strapped)
- Condition: TPO rolls OK; ISO wrap torn on 2 bundles but boards appear dry
- Exceptions: Y (“Short 6 bundles ISO; wrap torn on 2 bundles”) signed on BOL
- Photos: Y (BOL w/ notes, roof staging, torn wrap)
- Received by: A. Lopez
- Action: Supplier to deliver remaining 6 bundles by 1/30; PM notified to adjust crew plan if late
Practical takeaway: Always separate what arrived from what was expected. Partial deliveries are normal; undocumented partials are expensive.
Example 3: Damaged goods that should trigger a credit
- Date: 1/29/26
- Area: Basement electrical room
- Time: Arrive 10:30 a.m. / Unload complete 11:05 a.m.
- Supplier: Graybar
- Carrier/Driver: FedEx Freight
- Materials: Panelboard P1, breakers (cartons)
- Qty: 1 panelboard crate, 6 cartons breakers
- PO #: 55890
- BOL #: FX99201
- Drop location: Basement staging (secured)
- Condition: Panelboard crate punctured on side; internal packing exposed; possible damage
- Exceptions: Y (“crate punctured; contents may be damaged”) on BOL
- Photos: Y (wide + close-up + label + BOL)
- Received by: J. Patel
- Action: Quarantined crate; supplier contacted for inspection/replacement; AP told to hold payment pending resolution
Money connection: the log entry tells AP exactly why the invoice can’t be paid “as-is,” and it gives procurement leverage to get a replacement fast.
Common Mistakes
These are the mistakes that turn material receipt documentation into a useless diary instead of a tool that protects cost.
- No PO or ticket number If your log says “delivered conduit,” AP can’t match it. Then they either:
- Pay the wrong invoice, or
- Interrupt you for details when you’re already buried
Fix: Make PO/ticket a required field. If you don’t have it, take a photo of the paperwork and write “PO unknown—ticket photo captured.”
- Ignoring partial deliveries A “delivery received” note hides shortages and backorders.
Examples you must document:
- Only 6 of 10 doors delivered; remaining 4 backordered.
- 2 pallets of tile delivered, but thinset and trim were not.
Fix: Write expected vs. received. Use clear language: “Short X,” “Backordered Y,” “To be delivered on date.”
- Condition notes that are too vague “Damaged” without details doesn’t help. Neither does “OK” when it was raining and the material was uncovered.
Fix: Describe the damage type and location: “water exposure on top layer,” “crushed corners,” “broken banding,” “fork puncture.”
- No photos, or photos that don’t prove anything A blurry close-up without context is easy to argue with.
Fix: Take 3–4 photos that tell a full story (wide, medium, close-up, paperwork). Include labels/serial numbers when available.
- Not looping in accounts payable early This is where money leaks. If AP pays before credits are issued, the “field problem” becomes an accounting mess.
Fix: Same-day message: “Hold payment on PO #____ due to shortage/damage. Photos attached. Replacement/credit requested.”
FAQ
Q: What’s the minimum I should record for material delivery tracking construction?
A: Date, time, supplier, material + quantity, PO/ticket number, drop location, and condition on arrival. If there’s any issue, add exceptions on the BOL and photos.
Q: How do I handle a delivery when I can’t safely count everything?
A: Record quantities as “per ticket” and note “not opened/verified.” Take photos of labels and the ticket. If you later find a shortage, you can show you didn’t certify the count.
Q: Who should sign delivery tickets on site?
A: Ideally the person who inspected the load (super, foreman, or designated receiver). If laborers sign, train them to (1) look for damage, (2) note shortages, and (3) never sign “received in good condition” if it’s not true.
Q: What if the driver won’t wait for inspection?
A: Don’t get into a shouting match. Do a quick visible check, write “subject to inspection” if allowed, photograph the load immediately, and notify the supplier the same day. The key is showing you acted fast.
Q: How does delivery documentation connect to getting paid correctly?
A: Your daily logs support what costs belong to the job and what costs should be credited back. When PO numbers, quantities, and condition notes are documented, AP can approve the right invoices, hold the wrong ones, and recover credits without weeks of back-and-forth.